Cable Trench Dewatering Well Point System Method of Statement

Dewatering is the temporary reduction of pore pressures or groundwater levels to provide dry, stable and safe soil conditions in excavations below groundwater level. On a construction project dewatering is used to facilitate the construction of the deep excavations that are required for foundations, basements, trenches and other underground structures. Recommended Dewatering Type As per… Read More »

Testing & Commissioning Method Statement for Footfall Visitor Counting System

The User Acceptance tests will demonstrate that the system and related materials have been correctly installed and that the footfall system will operate in a manner that will enable client to accept it as a working system and proceed with the process of using it. Purpose of the User Acceptance Tests (UAT) in this document… Read More »

Trench Preparation Excavation and Backfill Method Statement for Electric Underground Cable Laying

The purpose of this document is to specify the procedure for excavation backfilling and trench preparation for installation of 132 kV cables and fiber optic Cables. Roles & Responsibilities Project Manager: Lead all construction activities and enforce strict adherence to all procedures. Site Manager: Lead the construction activities at site and report to the Project… Read More »

Method Statement for Firefighting Piping Equipment and Accessories Installation

This method statement for fire fighting system covers below activities: Piping system installation Fire fighting equipment and accessories installation Installation of pumps Flushing/Cleaning of piping and equipment Installation of fire detection system and accessories Quality of installation and materials at site will be ensured by project team consisting of a Project Manager, Project Engineers, QA… Read More »

Surge & Lightning Protection Earthing Grounding System Installation

The aim of this method statement is to describe electrical works associated with installation of earthing / grounding system, lightning surge protection systems. The grounding & lightning protection system are designed to ensure the complete safety of both persons and equipment throughout the project buildings and facilities. Storage of exothermic welding materials should be in… Read More »

Method of Statement for Parapet Wall / Roof Construction

This method statement will help to describe the procedure to for parapet wall / roof construction works, that ultimately will ensure that the work is planned and performed in accordance with project technical specifications and drawings. The project manager will be responsible for overall activities. The work will be carried out under the responsibility of… Read More »

Method Statement for Sheet Piling Works

This method statement describes the method and procedures involved in the installation of sheet pile wall (as per approved drawings) as temporary shoring and facilitate the work relating to the construction works. The technical specification and other relevant information on machinery and equipment used in this works are included. The installation of sheet piles are… Read More »

Boom Truck Operators Instructions on Construction Projects

This Instruction addresses the training of new boom truck operators including the refresher awareness and training of experienced operator. This Instruction applies to all operators of boom trucks on construction project sites. All Boom Truck operators must hold a valid license before operating the truck at project sites. Also as an additional safety requirement, where… Read More »