Category Archives: Construction Method Statement

Grease Trap Installation Procedure

This method of statement specifies the detailed requirements and procedures for the grease trap installation for the building or any kind of project. Strictly follow the manufacturers Health & Safety recommendations for handling and use of the grease trap units and accessory materials. Site team shall ensure that all the operatives are aware of the… Read More: Grease Trap Installation Procedure »

Method Statement for Cutting and Recasting of Strap Beam

1. Purpose The purpose of this method statement is to define the procedure for safe cutting, demolition, modification, and recasting of reinforced concrete strap beams in accordance with approved structural drawings, consultant instructions, project specifications, and applicable construction standards. This procedure ensures that all structural alteration works are executed safely without affecting the integrity and… Read More: Method Statement for Cutting and Recasting of Strap Beam »

PDA Test Procedure / PDA Testing On Bored Pile / Micro Pile

Below document describes instructions and guidelines for PDA Testing On Bored Piles / Micro Piles. The PDA/CAPWAP system was developed by Pile Dynamics Inc, Ohio, USA and has been in use for more than 15 years. PDA field data acquisition and computer unit has its own in-built self checking system and all force and acceleration… Read More: PDA Test Procedure / PDA Testing On Bored Pile /… »

Method Statement for Installation of Earthing & Lightning Protection System

This  electrical method  statement covers the nature and type of work for  the Earthing  & Lightning Protection System installation as per site requirements for the project. The piles and vertical re-bars are provided with connections for Earthing & Lightning Protection System installation by main contractor. Any core drilling, chipping, excavation and back filling work required… Read More: Method Statement for Installation of Earthing & Lightning Protection System »

Sequences and Methodology for Installation of MEP System for Water Treatment Plant

This method of statement specifies the sequences and methodology for the installation of MEP system for Water Treatment Plant. All workers associated with the installation of MEP for Water treatment plant will be responsible in accordance with the contract requirements and project specifications. All workers shall wear PPE as per risk assessment and project HSE… Read More: Sequences and Methodology for Installation of MEP System for Water… »

Hot Work Permit System HSE Management Procedure – PTW Permit To Work System

This standard document describes the permit to work system to control potentially high risk hot work operations through the issue of a Hot Work Permit. By implementing this safe work instruction organization shall ensure a safe place to work when undertaking hot works on any type and size of project. Additional control measures may be… Read More: Hot Work Permit System HSE Management Procedure – PTW Permit… »

Wall & Flooring Tiles Installation Method Statement

The purpose of this civil work method statement is to outline and describe in detail the procedure such as setting and lay-out plan on actual location, laying of tiles, mixing of mortar tile grout, final laying of tiles and all other related activity. This flooring tiles activity should be performed with strict compliance and implementation… Read More: Wall & Flooring Tiles Installation Method Statement »

Firefighting Pump Set Installation, Testing & Commissioning Method Statement

Below is a precise firefighting pump installation testing and commissioning method statement which is very useful as a guide for plumbing or firefighting engineers working on a construction project. Below is list of equipment and tools: Mechanical Tools Spanner Set Grooving / Threading Machine Valve opening keys Test gauges Tachometer Multi Meter Dial gauge Pressure… Read More: Firefighting Pump Set Installation, Testing & Commissioning Method Statement »