Gl Conduits & Accessories Installation for Electrical and ELV Services

Gl Conduits & Accessories Installation for Electrical and ELV Services

On this page you shall find method statement for electrical conduit installation. This  electrical method statement covers the nature and type of work for the Gl conduits & accessories installation for the following systems as applicable on the projects. Lighting Control Small

2025
Dec
12

Trench Preparation Excavation and Backfill Method Statement for Electric Underground Cable Laying

backfilling and compaction of trench for direct buried cable

The purpose of this document is to specify the procedure for excavation backfilling and trench preparation for installation of 132 kV cables and fiber optic Cables. Roles & Responsibilities Project Manager: Lead all construction activities and enforce strict adherence to all procedures.

2025
Nov
19

Testing & Commissioning Method Statement for Footfall Visitor Counting System

The user acceptance tests will demonstrate that the system and related materials have been correctly installed and that the footfall system will operate in a manner that will enable client to accept it as a working system and proceed with the process

2025
Nov
14

Safe Evacuation Procedure in Electrical Emergency Situation

Safe Evacuation Procedure in Electrical Emergency Situation

This procedure is designed to carry out a safe evacuation of operatives from electrical emergency situation which may happen during the energization of the switchgear/DB’ s in a construction project. The special conditions of working on a live system makes it vital

2025
Oct
10

Surge & Lightning Protection Earthing Grounding System Installation

Connect earth rod to bare copper wire

The aim of this method statement is to describe electrical works associated with installation of earthing / grounding system, lightning surge protection systems. The grounding & lightning protection system are designed to ensure the complete safety of both persons and equipment throughout

2025
Jul
26

Method Statement for Cable Laying and Termination for Control and Signal Cables

The purpose of this method statement is to provide general guidelines for cable laying and cable termination for control and signal cables. Scope of this method statement covers the followings activities. material handling procedure precaution testing inspection The following documents are considered

2025
Jul
7

Structured Cable Installation Method Statement

Structured Cable Installation Method Statement

Below is an electrical method statement for the installation of structured cable / network cabling system (IPTV, MC, CCTV & ACCESS CONTROL) as per the project specifications and manufacturer installation instructions. System is also known as it structured cabling. Arrange below tools

2024
Jun
9

Electrical Switchgear Installation Method Statement for 11KV HV Panel

Below is a precise method of statement for electrical works, that explains and covers the installation & inspection of 11KV switchgear panels on already approved and ready base/plinth. Switchgear installation shall be done in compliance with the project electrical specifications and switchgear