Tag Archives: Backfilling for Storm Sewer

Sewer System Sewerage Piping Installation & Testing Method Statement

All the piping materials received at site will be inspected, upon receipt on the project site. Any discrepancies / damages should be notified and reported to the supplier for further action. Materials found not suitable for site use will be removed from site immediately. All construction/inspection/testing works shall be carried out in accordance with project… Read More »

Method of Statement for Structural Excavation and Backfilling

The purpose of this method statement is to define the standard work process for Structural Excavation and Backfilling related activities. Method of statement addresses work operation associated with structural excavation and backfilling. All necessary setting out, tree cutting, clearing and grubbing will be completed prior to performing this operation. This work consists of excavation for… Read More »